Kalmar County

Torsås

Torsås municipal executive committee gave SunSpark Nordic AB a positive planning decision on 24 March 2026 for a data centre of about 10,000 square metres on the property Övraby 1:98 in Söderåkra. The detailed plan is to be drawn up at the applicant's expense. No power capacity is given.

The site is 2.6 hectares of pasture by Pårydsvägen, within a national interest for total defence (weather radar impact zone). The minutes expect 50 to 60 jobs plus about ten in ongoing management, and say connection to district heating and municipal water at Pårydsvägen is possible.

According to the minutes, the company has also applied for a 167-hectare solar park, handled by the county administrative board. On 7 September 2026 the municipality registered new site proposals from the company, with 4.5 and 15.2 hectares in their titles. They are not published.

Data centre, Hylte (Hyltebruk, Västra Åkralt) — In developmentPanattoni data centre, Hässleholm Nord — ProposedGoogle Torsboda, Timrå — AnnouncedEcoDataCenter Smedjebacken (Röbacken) — In developmentFossefall AI factory, Jokkmokk — In developmentEcoDataCenter Norrsundet (Gävle) — ProposedData centre, Ockelbo (Vallhalla, Lingbo) — In developmentTherma Loop data centre, Halmstad (Kistinge) — ProposedSunSpark data centre, Gotland (Visby) — ProposedMagnora data centre, Tranemo (Limmared) — ProposedSunSpark data centre, Torsås (Söderåkra) — ProposedPlanned data centre, Enköping (Ullunda) — ProposedMagnora data centre, Hultsfred (Nyhagen) — ProposedRoofscapes data centre, Bräcke — AnnouncedVerda AI centre, Sundsvall (Almåsen) — AnnouncedEdgeConneX Skellefteå — In developmentMeta Luleå — OperationalGoogle Horndal — Under constructionMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalMicrosoft Staffanstorp — OperationalEcoDataCenter Falun — Partially operationalEcoDataCenter Borlänge — Under constructionatNorth SWE01 Kista — OperationalatNorth SWE02 Akalla — In developmentatNorth SWE04 Sollefteå — In developmentEquinix SK1 — OperationalEquinix SK2 — OperationalEquinix SK3 — OperationalConapto Stockholm 3 North — OperationalDigital Realty Stockholm — OperationalSTACK STO01 Stockholm — OperationalBahnhof Pionen — OperationalBahnhof Thule — OperationalBahnhof Gullan — OperationalBahnhof S:t Erik — OperationalBahnhof Sparven — OperationalConapto Stockholm South — OperationalGleSYS Falkenberg — OperationalGleSYS Stockholm — Operationalevroc Arlandastad — Under constructionHydro66 Svenska, Boden — Operational

Documented projects in the register

Questions for a concrete establishment

  • Has a plan-cost agreement been signed with SunSpark?
  • Does the site change after the September proposals?
  • What grid capacity and connection date can the site get?