Google’s first data center in Sweden, under construction in Horndal in Avesta municipality, on 109 hectares that Google bought from the municipality in 2017. Ground work started in November 2025, Google announced the build on 2 June 2026 and it aims to finish in 2028. SVT reports that Google has been granted an environmental permit, a site-works permit and a building permit, and that the site will have 100 permanent jobs. Google has not published a power figure.

Under constructionGrid: Not published as a numbered connection on the cited Google pages. The location page mentions access to clean and reliable electricity. The 2 June 2026 blog’s 700 MW sentence is about Swedish renewable PPAs since 2013, not Horndal site or IT power.

Show on the map →

Fact box

Actor
Google
Status
Under construction
Municipality / county
Avesta · Dalarna County
Bidding zone
SE3
Last checked
2026-11-11
Location accuracy
Municipality level
EcoDataCenter Smedjebacken (Röbacken) — In developmentEcoDataCenter Norrsundet (Gävle) — ProposedData centre, Ockelbo (Vallhalla, Lingbo) — In developmentPlanned data centre, Enköping (Ullunda) — ProposedVerda AI centre, Sundsvall (Almåsen) — AnnouncedMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalEcoDataCenter Falun — Partially operationalEcoDataCenter Borlänge — Under constructionatNorth SWE01 Kista — OperationalatNorth SWE02 Akalla — In developmentEquinix SK1 — OperationalEquinix SK2 — OperationalEquinix SK3 — OperationalConapto Stockholm 3 North — OperationalDigital Realty Stockholm — OperationalSTACK STO01 Stockholm — OperationalBahnhof Pionen — OperationalBahnhof Thule — OperationalBahnhof Gullan — OperationalBahnhof S:t Erik — OperationalConapto Stockholm South — OperationalGleSYS Stockholm — Operationalevroc Arlandastad — Under constructionAvesta100 km
Approximate Horndal locality pin in Avesta Municipality. Building coordinates are not published here.

Phases

  • Horndal facility — Under construction

Capacity disclosure

  • IT power

    Not stated in the cited sources

    IT power · current · 2026 · announced · campus

    Unclear / conflictingAs of 2026-09-11 · Google Data Centers

    Checked the Horndal location page, the 2 June 2026 blog and the same-day press notice. No campus megawatt is stated. Directory figures are not imported.

Planning and grid

According to SVT on 2 June 2026, Google has applied for and been granted an environmental permit, a site-works permit (marklov) and a building permit. The permit decisions themselves, with dates and scope, are not read here. Avesta municipality writes that the enquiry came through Business Sweden before Christmas 2014 and that Horndal became the main site during the winter of 2014–2015, partly because of its strong connection to electricity infrastructure.

Not published as a numbered connection on the cited Google pages. The location page mentions access to clean and reliable electricity. The 2 June 2026 blog’s 700 MW sentence is about Swedish renewable PPAs since 2013, not Horndal site or IT power.

Upcoming decisions and dates

  • 2028 · Company target

    Target completion for Google’s data center in Horndal

    Google broke ground in June 2026. Its location page gives 2028 as the target completion date and notes that the timeline can change.

    Source: Google Data Centers

The full decision calendar →

Updates

  • 2026-06-02

    Google says it broke ground on a Horndal data center

    Google’s 2 June 2026 blog and press notice say it broke ground in Horndal. The location page later states construction is underway, with a target completion date of 2028. No campus megawatt is stated on those pages.

Context

More projects in Dalarna County

Related news

Knowledge gaps

  • Google has not published a power figure for Horndal.
  • The permit decisions are not read here, so their dates and scope are not confirmed.
  • No grid-connection agreement for the site is published in the cited sources.

Sources

  1. Horndal, Sweden – Google Data Center Location — Google Data Centers, 2026-09-01. Checked 2026-09-11.
  2. Blue, yellow and green: Google invests in its new data center in Sweden — Google, 2026-06-02. Checked 2026-09-11.
  3. Google Breaks Ground on Data Center in Horndal, Sweden — Google Cloud Press Corner, 2026-06-02. Checked 2026-09-11.
  4. SVT Nyheter Dalarna: The announcement: Google builds data centre in Horndal — SVT Nyheter Dalarna, 2026-06-02. Checked 2026-11-11.
  5. Avesta municipality: Google: when Horndal entered the picture — Avesta kommun, 2026-09-30. Checked 2026-11-11.

Submit a documented update · Report an error