Stockholm · Stockholm County · SE3
atNorth SWE02 Akalla
atNorth Stockholm metro site in Akalla. On 29 January 2026 atNorth announced plans to build SWE02 as a 30 MW metro site complementary to SWE01, scheduled to go live in Q4 2027. The SWE02 page restates 30 MW site power capacity. That figure is stored as announced or planned site power. It is not treated as live IT load or as a reviewed grid agreement.
Fact box
- Actor
- atNorth
- Last checked
- 2026-09-11
- Location accuracy
- district · Approximate location
Approximate Akalla district location.
Phases
- SWE02 — In development
Capacity disclosure
Site power
30 MW
Site power · announced / planned · 2026 · announced · campus
ReportedAs of 2026-01-29 · atNorth
Operator announcement of 29 January 2026. The SWE02 page restates “30 MW Site power capacity”. Not treated as live IT load or as a reviewed grid contract.
“will be a 30MW metro site”
Planning and grid
Target live date Q4 2027 is operator-reported. Building-permit status is not verified here.
The 29 January 2026 notice says Ellevio will construct a new electrical substation. That is operator-reported counterpart language. It is not filed here as a numbered connection agreement or contracted import.
Updates
2026-01-29
atNorth announces a 30 MW SWE02 metro site in Stockholm
On 29 January 2026 atNorth announced plans to build SWE02 as a 30 MW metro site in Akalla, scheduled to go live in Q4 2027. Stored as announced site power, not as live IT load.
Knowledge gaps
- Occupied or commissioned IT load is not published.
- Live date is a schedule, not a commissioning record.
- Ellevio substation wording is not a numbered connection agreement in the cited pages.
Sources
- Sweden data centers — atNorth, 2026-01-01. Checked 2026-09-10.
- New 30MW metro data center in Stockholm, Sweden — atNorth, 2026-01-29. Checked 2026-09-11.
- SWE02 Stockholm metro site — atNorth, 2026-01-29. Checked 2026-09-11.