Stockholm · Stockholm County · SE3

Conapto Stockholm South

Conapto campus comprising Stockholm 2 South and Stockholm 4 South. A 5 September 2024 company release said Stockholm 4 South had opened and that the campus offered 5,200 m² of computer rooms and 24 MW of power. A data sheet for Stockholm 2 South states five computer rooms with 4 MW total capacity. On 24 June 2026, Conapto reported initial CoreWeave capacity online at Stockholm 4 South under a colocation agreement; customer-specific MW were not stated.

OperationalGrid: Campus power is operator-stated at 24 MW in the 2024 opening release. Agreement documents are not published here.

Fact box

Actor
Conapto
Last checked
2026-09-12
Location accuracy
municipality · Approximate location

Municipality-level pin for the south campus. Contact address on data sheets is not treated as the hall coordinate.

Phases

  • Stockholm 2 SouthOperational
  • Stockholm 4 SouthOperational

Capacity disclosure

  • Site power

    24 MW

    Site power · announced / planned · 2024 · announced · campus

    ReportedAs of 2024-09-05 · Conapto / Mynewsdesk

    total capacity of 5 200 m² of computer rooms and 24 MW of power

  • Announced capacity (definition unclear)

    4 MW

    Announced capacity (definition unclear) · announced / planned · 2026 · designed · building

    ReportedAs of 2026-09-10 · Conapto

    Phase figure. Not added on top of the 24 MW campus figure.

    five computer rooms with a total capacity of 4 MW

Planning and grid

Operating campus after the 2024 opening announcement. Permit files not reviewed here.

Campus power is operator-stated at 24 MW in the 2024 opening release. Agreement documents are not published here.

Updates

  • 2026-06-24

    Conapto announces a CoreWeave colocation agreement

    The announcement covers two Stockholm campuses and reports initial capacity online at Stockholm 4 South. Customer-specific MW are not stated.

  • 2024-09-05

    Conapto says Stockholm 4 South has opened

    Conapto’s 5 September 2024 release said Stockholm 4 South had opened and that the south campus offered 5,200 m² and 24 MW together with Stockholm 2 South.

Knowledge gaps

  • IT versus facility definition for 24 MW is not fully specified.
  • Other Conapto halls are not each profiled in this launch set.

Sources

  1. Conapto opens Stockholm 4 South Conapto / Mynewsdesk, 2024-09-05. Checked 2026-09-10.
  2. Data sheet: Stockholm 2 South Conapto, 2024-01-01. Checked 2026-09-10.
  3. CoreWeave and Conapto announce a Swedish colocation agreement Conapto, 2026-06-24. Checked 2026-09-12.

Submit a documented update · Report an error