Hässleholm · Skåne County · SE4

Panattoni data centre, Hässleholm Nord

Proposed hyperscale data centre of about 300 MW in two stages at Hässleholm Nord, Skåne. The municipal executive committee approved a non-binding letter of intent with the property developer Panattoni on 10 June 2026, reserving about 20 hectares. E.ON has given a first positive connection indication of 150 MW for around 2033, which is also the preliminary target for opening.

ProposedGrid: E.ON has given a first positive connection indication of 150 MW for around 2033. Panattoni intends to apply for a further 150 MW. E.ON's grid study is expected to take 6 to 18 months, followed by a preliminary study of 3 to 9 months. An indication is not a connection agreement.

Show on the map →

Fact box

Status
Proposed
Municipality / county
Hässleholm · Skåne County
Bidding zone
SE4
Announced capacity (definition unclear)
300 MW · Hässleholms kommun
Last checked
2026-11-11
Location accuracy
Municipality level
Data centre, Hylte (Hyltebruk, Västra Åkralt) — In developmentTherma Loop data centre, Halmstad (Kistinge) — ProposedSunSpark data centre, Gotland (Visby) — ProposedMagnora data centre, Tranemo (Limmared) — ProposedSunSpark data centre, Torsås (Söderåkra) — ProposedMagnora data centre, Hultsfred (Nyhagen) — ProposedMicrosoft Staffanstorp — OperationalBahnhof Sparven — OperationalGleSYS Falkenberg — OperationalHässleholm100 km
Approximate pin for the Hässleholm Nord development area north of Hässleholm town. The exact plot is not published.

Phases

    Capacity disclosure

    • Announced capacity (definition unclear)

      300 MW

      Announced capacity (definition unclear) · announced / planned · 2026 · announced · campus

      DocumentedAs of 2026-11-02 · Hässleholms kommun

      Planned power at full build-out in two stages of about 150 MW each. The municipality's page does not say whether the figure is IT load or grid connection.

      “Planerad effekt: 300 megawatt”

    Planning and grid

    Letter of intent approved by the municipal executive committee on 10 June 2026 (item 126). It is not legally binding and either party can end it. The municipality is changing the detailed plan for a new main entrance to Hässleholm Nord from the Stoby interchange via Stobyvägen; no date is given for that plan.

    E.ON has given a first positive connection indication of 150 MW for around 2033. Panattoni intends to apply for a further 150 MW. E.ON's grid study is expected to take 6 to 18 months, followed by a preliminary study of 3 to 9 months. An indication is not a connection agreement.

    Upcoming decisions and dates

    • Around 2033 · Company target

      Preliminary target for opening Panattoni’s data centre at Hässleholm Nord

      Hässleholm municipality gives around 2033 as the preliminary target for opening, the same year as E.ON’s first connection indication of 150 MW. The letter of intent is not binding.

      Source: Hässleholms kommun

    The full decision calendar →

    Updates

    • 2026-06-10

      Hässleholm approves letter of intent with Panattoni on a 300 MW data centre

      The municipal executive committee approved a non-binding letter of intent (item 126) to investigate a hyperscale data centre in two stages at Hässleholm Nord. E.ON has given a first positive connection indication of 150 MW for around 2033.

    Context

    More projects in Skåne County

    Knowledge gaps

    • Whether 300 MW refers to IT load or grid connection is not stated.
    • No operator or tenant for the data centre is named.
    • The second 150 MW has no connection indication yet.
    • Investment size is not disclosed.