Dalarna County · SE3
Falun
Which Falun megawatt is commissioned, which is a 2026 target, and which is available-power marketing? Falun is the municipality of EcoDataCenter 1. The 2025 annual report is the dated source for commissioned versus under-construction buildings: C and D commissioned, site capacity 29 MW to 41 MW as of the balance-sheet date, E and F in construction with a stated 65 MW once operational. Marketing pages state 80 MW available power. Those rows are not added. The campus is partially operational in this register.
Read the 2025 annual-report extract first. Read the Falun site page second. Read the 80 MW press item third as a designed or future-supply sentence, not as a commissioned total. Read Borlänge fourth so the two municipalities stay separate. Read SE3 fifth. Then ask Falun municipality for current detailed-plan coverage of buildings E and F. The operator publishes Slaggvarpsvägen 21 on the site page; that is an address hook, not a surveyed outline in this file.
A company press item describes securing 80 MW future power supply with Falu Energi & Vatten and Ellevio. That is operator-reported. It is not filed here as a reviewed grid agreement. Heat-recovery language with Falu Energi & Vatten is a described arrangement until delivered heat is quantified. This register does not publish a Falun heat megawatt-hour series. Boverket’s detaljplan guidance explains why plan coverage for E and F is a municipal question.
Keep the metric definitions unfinished where the source is unfinished. The extracted report wording does not fully specify whether 41 MW or 65 MW is IT load or facility load. The 80 MW site-page sentence is stored as designed or available power. E and F completion dates in the report are targets, not commissioning certificates. Adding those three numbers produces a figure that no cited source published.
Common misreads: using 80 MW as today’s commissioned IT load; using 65 MW as a present total; treating Falun and Borlänge as one campus; treating heat-recovery copy as delivered annual heat; treating SE3 as residual capacity on Slaggvarpsvägen. Another misread is to treat the campus as fully operational when E and F are still in construction in the dated report.
Ask for the latest commissioned-building list, not only the campus envelope. Separate Falu Energi & Vatten heat statements from delivered heat. Check current detailed-plan coverage for buildings E and F. Ask which paper Ellevio or the local owner has issued, and whether it matches the 80 MW sentence. Ask how Falun relates to Borlänge without double-counting.
SE3 membership is shared with Stockholm County and does not merge Falun into the Kista interconnect story. Stockholm Data Parks and Stockholm Exergi are a different municipal heat pattern. Falu Energi & Vatten is the named local utility in operator copy. Those names are not interchangeable. A 41 MW commissioned-row sentence is still not an IT-versus-facility definition. A 65 MW later-campus sentence is still a target. An 80 MW available-power sentence is still an envelope.
If a later annual report restates commissioned buildings, replace the 2025 row with that later dated row. Do not keep 41 MW as current after a newer commissioned figure appears. Until then, this file’s current commissioned step is the balance-sheet-date 41 MW sentence. E and F remain construction with company target dates. Unknown delivered heat stays unknown.
This municipality brief proves that Falun has a dated operator megawatt series with distinct commissioned, target and envelope rows. It does not prove E and F are operational, does not prove delivered heat, and does not invent another Falun hall.
Documented projects in the register
- EcoDataCenter Falun — Partially operational
Questions for a concrete establishment
- Ask for the latest commissioned-building list, not only the campus envelope.
- Separate Falu Energi & Vatten heat statements from delivered heat.
- Check current detailed-plan coverage for buildings E and F.
- Are 41 MW, 65 MW and 80 MW being kept as dated rows with their definitions unfinished where the source is unfinished?
- Which network-owner paper, if any, sits behind the 80 MW future-supply sentence?
- Is Borlänge being counted again inside this Falun total?
Sources
- EcoDC Holding AB annual report 2025 (English) — EcoDC Holding AB, 2026-04-01. Checked 2026-09-10.
- EcoDataCenter 1, Falun — EcoDataCenter, 2026-01-01. Checked 2026-09-10.
- EcoDataCenter in Falun secures a future power supply of 80 MW — EcoDataCenter, 2020-01-01. Checked 2026-09-10.
- Detailed development plans — Boverket, 2024-10-17. Checked 2026-09-10.