Uppsala County · SE3

Enköping

Enköping municipality has received an external request to establish a data centre on the municipal property Ullunda 8:1>2. On 30 September 2026 the planning, land and development committee started a development project for the site up to the adoption of a detailed plan. The developer pays the pre-study costs under a preliminary agreement. The developer is not named.

The site is farmed today and marked as a future housing area in the in-depth comprehensive plan for Enköping. The memo names postglacial clay and the national interest in farmland as risks. Detailed-plan work is expected to start in the fourth quarter of 2026 if a planning decision is granted.

On 20 October 2026 the chief executive of ENA Energi briefed the executive board on the agreement set-up with Conapto: a cooperation agreement and a delivery agreement, expected to be finished in early 2027. ENA Energi's interim report says the company is studying waste heat from a planned data hall in Enköping. Vattenfall, E.ON and Svenska kraftnät briefed the board the same day on grid capacity in the municipality and the region.

Data centre, Hylte (Hyltebruk, Västra Åkralt) — In developmentPanattoni data centre, Hässleholm Nord — ProposedGoogle Torsboda, Timrå — AnnouncedEcoDataCenter Smedjebacken (Röbacken) — In developmentFossefall AI factory, Jokkmokk — In developmentEcoDataCenter Norrsundet (Gävle) — ProposedData centre, Ockelbo (Vallhalla, Lingbo) — In developmentTherma Loop data centre, Halmstad (Kistinge) — ProposedSunSpark data centre, Gotland (Visby) — ProposedMagnora data centre, Tranemo (Limmared) — ProposedSunSpark data centre, Torsås (Söderåkra) — ProposedPlanned data centre, Enköping (Ullunda) — ProposedMagnora data centre, Hultsfred (Nyhagen) — ProposedRoofscapes data centre, Bräcke — AnnouncedVerda AI centre, Sundsvall (Almåsen) — AnnouncedEdgeConneX Skellefteå — In developmentMeta Luleå — OperationalGoogle Horndal — Under constructionMicrosoft Gävle — OperationalMicrosoft Sandviken — OperationalMicrosoft Staffanstorp — OperationalEcoDataCenter Falun — Partially operationalEcoDataCenter Borlänge — Under constructionatNorth SWE01 Kista — OperationalatNorth SWE02 Akalla — In developmentatNorth SWE04 Sollefteå — In developmentEquinix SK1 — OperationalEquinix SK2 — OperationalEquinix SK3 — OperationalConapto Stockholm 3 North — OperationalDigital Realty Stockholm — OperationalSTACK STO01 Stockholm — OperationalBahnhof Pionen — OperationalBahnhof Thule — OperationalBahnhof Gullan — OperationalBahnhof S:t Erik — OperationalBahnhof Sparven — OperationalConapto Stockholm South — OperationalGleSYS Falkenberg — OperationalGleSYS Stockholm — Operationalevroc Arlandastad — Under constructionHydro66 Svenska, Boden — Operational

Documented projects in the register

Questions for a concrete establishment

  • When does the municipality apply for, and decide on, a planning decision for Ullunda 8:1>2?
  • Does ENA Energi's agreement with Conapto concern the Ullunda site?
  • What grid capacity can the grid owners offer a data centre in Enköping, and when?

About electricity area SE3 →

Related news

Sources

  1. Minutes, Enköping planning, land and development committee, 30 September 2026 (item 93, case KS2026/829) — Enköpings kommun (publication date not stated). Checked 2026-10-27.
  2. Memo: Direction decision (BP2), development project Ullunda 8:1, 14 September 2026 (case KS2026/829) — Enköpings kommun, 2026-09-14. Checked 2026-10-27.
  3. Minutes, Enköping municipal executive committee, 20 October 2026 (items 252 and 254) — Enköpings kommun, 2026-10-22. Checked 2026-10-27.
  4. ENA Energi AB interim report, January–August 2026 — ENA Energi AB / Enköpings kommun, 2026-09-16. Checked 2026-10-27.