Project changes

Material changes with a source. Not every rewritten press release.

  • 2026-11-12

    Hylte and Magnora set out next steps: E.ON grid, county permit, operation around 2029

    Hylte municipality confirmed that Magnora Data Center AB with subsidiaries holds the building permit. The grid installation is being designed with the regional network owner E.ON and requires a network concession; the operating permit is to be examined by the County Administrative Board of Halland. No investment decision has been taken; the first phase could start operating around 2029 if construction begins in the first half of 2027.

    Data centre, Hylte (Hyltebruk, Västra Åkralt)
  • 2026-11-10

    Fossefall signs grid connection agreement with Vattenfall Eldistribution for 65 MW in Jokkmokk

    Fossefall said it has signed a grid connection agreement with Vattenfall Eldistribution AB securing 65 MW for a planned AI factory in Jokkmokk, with the potential for a further 135 MW (200 MW in total). Construction is expected to start in Q2 2027; no final investment decision has been taken.

    Fossefall AI factory, Jokkmokk
  • 2026-11-06

    Telenor completes acquisition of control of Bahnhof; mandatory offer at SEK 62

    Telenor Sverige said it has completed the acquisitions of 57.5 percent of the shares and 87.9 percent of the votes in Bahnhof, operator of Bahnhof Pionen, and published an unconditional mandatory cash offer of SEK 62 per share. Acceptance period 9 November–7 December 2026; expected settlement 14 December 2026.

    Bahnhof Pionen
  • 2026-11-06

    Telenor completes acquisition of control of Bahnhof; mandatory offer at SEK 62

    Telenor Sverige said it has completed the acquisitions of 57.5 percent of the shares and 87.9 percent of the votes in Bahnhof, operator of Bahnhof Thule, and published an unconditional mandatory cash offer of SEK 62 per share. Acceptance period 9 November–7 December 2026; expected settlement 14 December 2026.

    Bahnhof Thule
  • 2026-11-06

    Telenor completes acquisition of control of Bahnhof; mandatory offer at SEK 62

    Telenor Sverige said it has completed the acquisitions of 57.5 percent of the shares and 87.9 percent of the votes in Bahnhof, operator of Bahnhof Gullan, and published an unconditional mandatory cash offer of SEK 62 per share. Acceptance period 9 November–7 December 2026; expected settlement 14 December 2026.

    Bahnhof Gullan
  • 2026-11-06

    Telenor completes acquisition of control of Bahnhof; mandatory offer at SEK 62

    Telenor Sverige said it has completed the acquisitions of 57.5 percent of the shares and 87.9 percent of the votes in Bahnhof, operator of Bahnhof S:t Erik, and published an unconditional mandatory cash offer of SEK 62 per share. Acceptance period 9 November–7 December 2026; expected settlement 14 December 2026.

    Bahnhof S:t Erik
  • 2026-11-06

    Telenor completes acquisition of control of Bahnhof; mandatory offer at SEK 62

    Telenor Sverige said it has completed the acquisitions of 57.5 percent of the shares and 87.9 percent of the votes in Bahnhof, operator of Bahnhof Sparven, and published an unconditional mandatory cash offer of SEK 62 per share. Acceptance period 9 November–7 December 2026; expected settlement 14 December 2026.

    Bahnhof Sparven
  • 2026-11-04

    atNorth and Calentix sign project development agreement on heat recovery to Långsele

    atNorth and Calentix said they have signed a project development agreement under which Calentix develops heat recovery from SWE04 to the Långsele district heating network, operated by Adven. Calentix gives 1.6 MW in the first phase, potential for about 20 MW, a heat purchase agreement targeted for 2027 and the second quarter of 2029 as the target for first heat delivery.

    atNorth SWE04 Sollefteå
  • 2026-11-03

    E.ON contracts Enersense for two 130 kV lines Hamre–Nässe, due March 2029

    Enersense said it has signed a contract with E.ON Energidistribution for two new 130 kV overhead lines, each about 2.5 kilometres, between the Hamre and Nässe substations in Sollefteå, with 35 new steel lattice towers. Work starts in November 2026 and is due to be completed in March 2029. Enersense links the lines to atNorth's planned 300 MW campus at Hamre.

    atNorth SWE04 Sollefteå
  • 2026-11-02

    Konkurrensverket clears Telenor's acquisition of control of Bahnhof

    Konkurrensverket left Telenor Sverige's acquisition of sole control of Bahnhof, operator of Bahnhof Pionen, without action (dnr 677/2026). According to Telenor all regulatory conditions are met; the acquisitions cover 57.5 percent of the shares and 87.9 percent of the votes and are expected to complete shortly.

    Bahnhof Pionen
  • 2026-11-02

    Konkurrensverket clears Telenor's acquisition of control of Bahnhof

    Konkurrensverket left Telenor Sverige's acquisition of sole control of Bahnhof, operator of Bahnhof Thule, without action (dnr 677/2026). According to Telenor all regulatory conditions are met; the acquisitions cover 57.5 percent of the shares and 87.9 percent of the votes and are expected to complete shortly.

    Bahnhof Thule
  • 2026-11-02

    Konkurrensverket clears Telenor's acquisition of control of Bahnhof

    Konkurrensverket left Telenor Sverige's acquisition of sole control of Bahnhof, operator of Bahnhof Gullan, without action (dnr 677/2026). According to Telenor all regulatory conditions are met; the acquisitions cover 57.5 percent of the shares and 87.9 percent of the votes and are expected to complete shortly.

    Bahnhof Gullan
  • 2026-11-02

    Konkurrensverket clears Telenor's acquisition of control of Bahnhof

    Konkurrensverket left Telenor Sverige's acquisition of sole control of Bahnhof, operator of Bahnhof S:t Erik, without action (dnr 677/2026). According to Telenor all regulatory conditions are met; the acquisitions cover 57.5 percent of the shares and 87.9 percent of the votes and are expected to complete shortly.

    Bahnhof S:t Erik
  • 2026-11-02

    Konkurrensverket clears Telenor's acquisition of control of Bahnhof

    Konkurrensverket left Telenor Sverige's acquisition of sole control of Bahnhof, operator of Bahnhof Sparven, without action (dnr 677/2026). According to Telenor all regulatory conditions are met; the acquisitions cover 57.5 percent of the shares and 87.9 percent of the votes and are expected to complete shortly.

    Bahnhof Sparven
  • 2026-10-30

    SMHI publishes response to EcoDataCenter's scoping and Seveso consultation for Gävle

    SMHI published its response (case 2026/2149/6.3.1, dated 5 October 2026) to the invitation to a scoping and Seveso consultation on an environmental permit application for a data centre in Gävle municipality; sender EcoDataCenter / Wescon. EcoDataCenter's consultation page names Norrsundet and asked for comments by 11 October 2026.

    EcoDataCenter Norrsundet (Gävle)
  • 2026-10-29

    Skellefteå issues partial start notice for EdgeConneX foundations

    According to Norran, the municipality issued a partial start notice on 29 October 2026 covering only the foundation works for phase one (DC01 and DC02). A start notice for the rest of the construction has not been reported.

    EdgeConneX Skellefteå
  • 2026-10-21

    Hylte grants building permits for a data centre and receiving station in Hyltebruk

    Hylte's community-development committee granted building permits for a data centre on Västra Åkralt 1:80 (item 91) and a control building with switchyard and transformer stations (item 90). The applicant states an installed IT capacity of about 60 MW.

    Data centre, Hylte (Hyltebruk, Västra Åkralt)
  • 2026-10-21

    Bräcke council sells land to Roofscapes

    The municipal council decided to sell parcels 4 and 6 of Bräcke 2:1 to Roofscapes AB for SEK 1,221,000 (item 106, case KSK 2025/539). The parcels are to be merged into Roofscapes' property Bräcke 4:4.

    Roofscapes data centre, Bräcke
  • 2026-10-21

    Sundsvall planning committee proposes adoption of the Almåsen detailed plan

    Under item 125 of its approved minutes, the urban planning committee proposed that the municipal council adopt the detailed plan for Vattjom 2:42 et al. under chapter 5, section 27 of the Planning and Building Act, and decided to remove an incorrect passage about correctional facilities from the plan documents. The council is expected to decide on 30 November 2026.

    Verda AI centre, Sundsvall (Almåsen)
  • 2026-10-20

    evroc now states up to 10,000 GPUs for Arlandastad

    The operator’s data-centers page, read 20 October 2026, says the Arlandastad facility is being built and states capacity for up to 10,000 GPUs, down from up to 16,000 in the February 2025 release. The page is undated, so the date of the change is not known.

    evroc Arlandastad
  • 2026-10-16

    Building permit granted for a data centre on Vallhalla 1:125 in Ockelbo

    Västra Gästriklands samhällsbyggnadsförvaltning granted a building permit for a data centre, offices, guardhouse, water treatment plant, sprinkler facility, garage, switchgear, transformer station, wall and parking on Vallhalla 1:125 (Fallåsvägen 51), case VGS-BYGG 2026-000365. A separate transformer-station permit followed on 23 October (VGS-BYGG 2026-000522).

    Data centre, Ockelbo (Vallhalla, Lingbo)
  • 2026-10-15

    Tranemo executive committee refers Magnora land case back for further preparation

    The municipal executive committee referred the case on selling about 35,000 square metres of part of Limmared 1:6 to Magnora for a data centre back to the general committee for further preparation to enable an establishment (item 203, case KS/2026:415). The administration had proposed a land allocation agreement.

    Magnora data centre, Tranemo (Limmared)
  • 2026-09-30

    Enköping starts development project for a data centre at Ullunda

    The executive board's planning, land and development committee told the land and development unit to run the development project on Ullunda 8:1>2 up to the adoption of a detailed plan (item 93, case KS2026/829). The municipality has received an external request to establish a data centre there. The developer is not named.

    Planned data centre, Enköping (Ullunda)
  • 2026-09-24

    Skellefteå grants building permit for EdgeConneX's DC01 and DC02

    The building and environment committee granted a permit for the new building DC02 and for converting DS4 and FA03 into DC01 on Ackumulatorn 3. A start notice is still required before construction.

    EdgeConneX Skellefteå
  • 2026-09-22

    Halmstad committee backs letter of intent on a data centre at Kistinge

    The municipal executive committee's community-development committee unanimously backed a letter of intent with Kistinge Infrastruktur AB, a subsidiary of Therma Loop AB, on Fyllinge 20:432 (case KS 2026/00451). The data centre needs at least 10 MW of connected power; the company has until 30 April 2027 to say whether it wants to buy the land.

    Therma Loop data centre, Halmstad (Kistinge)
  • 2026-09-02

    atNorth says CPP Investments and Equinix completed an acquisition

    atNorth announced that CPP Investments and Equinix completed an acquisition and that atNorth would continue under its existing brand. This is an ownership event, not a capacity or construction change.

    atNorth SWE01 Kista
  • 2026-09-01

    Hultsfred executive committee approves letter of intent with Magnora

    The municipal executive committee approved a letter of intent with Magnora Project Infra 2 AB on investigating a data centre on Verktyget 4 and 5 and part of Hultsfred 3:1 in the Nyhagen industrial area (item 108, case 2026/208). The working committee is to approve or reject step 1 before step 2 may begin. No land sale was decided.

    Magnora data centre, Hultsfred (Nyhagen)
  • 2026-08-25

    EcoDataCenter signs option on 52 hectares in Smedjebacken for a third campus

    EcoDataCenter said it has signed an option agreement to buy land in the Röbacken industrial area. It expects construction to start in 2027 once permits are granted and the first data center to be in operation in 2029.

    EcoDataCenter Smedjebacken (Röbacken)
  • 2026-08-17

    Sundsvall and Timrå councils approve sale of Torsboda Industrial Park to Google company

    Both councils approved the sale of Torsboda Industrial Park AB to DSC International AB on condition that the repurchase terms are renegotiated and clarified. A private individual has appealed Timrå's decision to the administrative court.

    Google Torsboda, Timrå
  • 2026-06-24

    Conapto announces a CoreWeave colocation agreement

    The announcement covers two Stockholm campuses and reports initial capacity online at Stockholm 4 South. Customer-specific MW are not stated.

    Conapto Stockholm South
  • 2026-06-10

    Hässleholm approves letter of intent with Panattoni on a 300 MW data centre

    The municipal executive committee approved a non-binding letter of intent (item 126) to investigate a hyperscale data centre in two stages at Hässleholm Nord. E.ON has given a first positive connection indication of 150 MW for around 2033.

    Panattoni data centre, Hässleholm Nord
  • 2026-06-02

    Google says it broke ground on a Horndal data center

    Google’s 2 June 2026 blog and press notice say it broke ground in Horndal. The location page later states construction is underway, with a target completion date of 2028. No campus megawatt is stated on those pages.

    Google Horndal
  • 2026-04-21

    Region Gotland allocates Visby Navaren 2 directly to SunSpark

    The regional executive board allocated the property Visby Navaren 2 directly to SunSpark Nordic AB and told the regional director to draw up a land allocation agreement valid for two years for a board decision (item 155, case RS 2026/259). The purpose is data centres co-located with solar parks.

    SunSpark data centre, Gotland (Visby)
  • 2026-03-24

    Torsås executive committee grants SunSpark a positive planning decision

    The municipal executive committee granted a positive planning decision for a data centre of about 10,000 square metres on Övraby 1:98 in Söderåkra and told the head of building and environment to sign a plan-cost agreement with SunSpark Nordic AB (item 74, case 2026/000064).

    SunSpark data centre, Torsås (Söderåkra)
  • 2026-02-23

    atNorth announces a 300 MW SWE04 plan in Sollefteå

    On 23 February 2026 atNorth confirmed plans to develop a 300 MW data center at Hamre Industrial Park, expected operational in H1 2028. Stored as announced site power, not as live IT load.

    atNorth SWE04 Sollefteå
  • 2026-02-11

    EcoDataCenter and Mistral AI announce a Borlänge partnership

    EcoDataCenter said it would design, build and operate an AI-focused data center at its existing Borlänge site, with Mistral deploying compute and a scheduled 2027 opening. The notice states a €1.2 billion long-term commitment. It is not stored as a second campus and does not publish a megawatt.

    EcoDataCenter Borlänge
  • 2026-02-05

    Sundsvall announces Verda's AI centre

    The municipality announced that Verda Cloud Oy is establishing an AI centre in Sundsvall municipality outside central Sundsvall, with Zoningpartners North AB leading preparations for construction start.

    Verda AI centre, Sundsvall (Almåsen)
  • 2026-01-29

    atNorth announces a 30 MW SWE02 metro site in Stockholm

    On 29 January 2026 atNorth announced plans to build SWE02 as a 30 MW metro site in Akalla, scheduled to go live in Q4 2027. Stored as announced site power, not as live IT load.

    atNorth SWE02 Akalla
  • 2025-12-31

    EcoDataCenter reports Falun C and D commissioned; site capacity 41 MW

    The 2025 annual report says data centers C and D were fully completed and commissioned and that Falun site capacity increased from 29 MW to 41 MW. E and F construction began in 2025.

    EcoDataCenter Falun
  • 2025-12-29

    Bräcke buys land for data-centre expansion and signs option with Roofscapes

    Under a purchase contract dated 29 December 2025 the municipality bought about 12.6 hectares of Bräcke 2:1 from the Church of Sweden to enable Vostroblock Group AB's development of a data centre, and signed an option agreement with Roofscapes AB.

    Roofscapes data centre, Bräcke
  • 2025-09-24

    EcoDataCenter starts construction at Kvarnsveden, Borlänge

    The operator said construction had started, with access to 250 MW at launch, a stated potential of 600 MW and the first data center due in early 2027. Added to the register on 20 October 2026.

    EcoDataCenter Borlänge
  • 2025-02-03

    evroc reports completed land purchase in Arlandastad

    evroc said it completed a purchase of 4,890 sqm building rights next to Stockholm Arlanda Airport, aiming to break ground in H1 2025 and operate in the latter half of 2026.

    evroc Arlandastad
  • 2024-09-05

    Conapto says Stockholm 4 South has opened

    Conapto’s 5 September 2024 release said Stockholm 4 South had opened and that the south campus offered 5,200 m² and 24 MW together with Stockholm 2 South.

    Conapto Stockholm South
  • 2021-11-16

    Microsoft opens the Sweden datacenter region

    Microsoft announced the Sweden region as open, with presence in Gävle, Sandviken and Staffanstorp and with Azure and Microsoft 365 available.

    Microsoft Gävle
  • 2020-10-01

    GleSYS says heat delivery to Falkenberg Energi has started

    A 1 October 2020 GleSYS release said surplus energy from the new Falkenberg hall had begun supplying district heat. That documents a start of delivery, not a later measured annual volume.

    GleSYS Falkenberg
  • 2018-12-12

    AWS opens Europe (Stockholm), eu-north-1

    AWS announced the Europe (Stockholm) Region as open, with three Availability Zones in Sweden. Municipal sites were not named on the launch blog.

    AWS Europe (Stockholm)