Checklists
What should a project team have in hand before it asks a municipality, network owner or adviser for a serious answer? Use this page to build a dated file, not to collect green ticks. Each item should end in a document, a named unanswered question or a clear statement that the research is incomplete. The lists do not classify your project for an authority.

General orientation. Assess the specific project separately. Applies to: Project teams preparing questions.
Start with a site brief
Before contacting institutions, write one version of the project facts: plot identity, intended use, phases, requested import capacity, voltage assumptions, cooling principle, water source, backup-fuel concept, operating hours, neighbours and target decision. Mark every number as requested, designed, announced, contracted or measured.
This brief is not a permit application or a connection offer. Its job is to stop different teams from asking different questions about different projects. Link each statement to a source or mark it as an assumption.
- Cadastral identity and land-control document.
- One-line project description and phase boundary.
- Requested load, voltage and connection point assumptions.
- Cooling, water, fuel, noise and operating-hour assumptions.
- Source, date and owner beside every material claim.
Power and planning file
Use the grid-connection and building guides next. Svenska kraftnät’s indicative map is context; it is not the property-level connection document. Boverket’s guidance explains the PBL vocabulary; the municipality’s file decides the project-specific status.
- Network owner and point of connection named.
- Latest written position dated and its status defined.
- Announced site power, IT load and grid capacity kept separate.
- Reinforcements, dependencies and payer identified.
- Plan instrument, status and decision body recorded.
- Building permit, startbesked and environmental tracks kept separate.
Environment, neighbours and delivery
A missing project-specific decision is not proof that no decision exists. Mark “not obtained” or “research incomplete” until the file supports a stronger statement. See due diligence, environmental permits, noise, water and municipal engagement for the next questions.
- Water source, annual and peak volumes, discharge or evaporation route.
- Fuel type, storage volume, test hours and emissions case.
- Noise matrix for cooling, generators, deliveries and construction.
- Neighbour and municipal dialogue log with dates and follow-ups.
- FDI scope note from counsel and current ISP material.
- Milestone table: permit, start, completion, energization and commissioning.
- Name the authority or counterpart for every open item.
- Attach the source and date, not only a slide reference.
- State whether each value is designed, reported or measured.
- Write the consequence of leaving a gap open.
- Set the next action and decision gate.
Sources
- Indicative transmission-network capacity map — Svenska kraftnät, 2026-01-01. Checked 2026-09-10.
- Planning and Building Act guidance — Boverket, 2026-01-01. Checked 2026-09-10.