Checklists

What should a project team have in hand before it asks a municipality, network owner or adviser for a serious answer? Use this page to build a dated file, not to collect green ticks. Each item should end in a document, a named unanswered question or a clear statement that the research is incomplete. The lists do not classify your project for an authority.

Construction cranes above a generic industrial building site.
Photo Sergej Karpow on Unsplash

General orientation. Assess the specific project separately. Applies to: Project teams preparing questions.

Start with a site brief

Before contacting institutions, write one version of the project facts: plot identity, intended use, phases, requested import capacity, voltage assumptions, cooling principle, water source, backup-fuel concept, operating hours, neighbours and target decision. Mark every number as requested, designed, announced, contracted or measured.

This brief is not a permit application or a connection offer. Its job is to stop different teams from asking different questions about different projects. Link each statement to a source or mark it as an assumption.

  1. Cadastral identity and land-control document.
  2. One-line project description and phase boundary.
  3. Requested load, voltage and connection point assumptions.
  4. Cooling, water, fuel, noise and operating-hour assumptions.
  5. Source, date and owner beside every material claim.

Power and planning file

Use the grid-connection and building guides next. Svenska kraftnät’s indicative map is context; it is not the property-level connection document. Boverket’s guidance explains the PBL vocabulary; the municipality’s file decides the project-specific status.

  • Network owner and point of connection named.
  • Latest written position dated and its status defined.
  • Announced site power, IT load and grid capacity kept separate.
  • Reinforcements, dependencies and payer identified.
  • Plan instrument, status and decision body recorded.
  • Building permit, startbesked and environmental tracks kept separate.

Environment, neighbours and delivery

A missing project-specific decision is not proof that no decision exists. Mark “not obtained” or “research incomplete” until the file supports a stronger statement. See due diligence, environmental permits, noise, water and municipal engagement for the next questions.

  • Water source, annual and peak volumes, discharge or evaporation route.
  • Fuel type, storage volume, test hours and emissions case.
  • Noise matrix for cooling, generators, deliveries and construction.
  • Neighbour and municipal dialogue log with dates and follow-ups.
  • FDI scope note from counsel and current ISP material.
  • Milestone table: permit, start, completion, energization and commissioning.
  1. Name the authority or counterpart for every open item.
  2. Attach the source and date, not only a slide reference.
  3. State whether each value is designed, reported or measured.
  4. Write the consequence of leaving a gap open.
  5. Set the next action and decision gate.

Sources

  1. Indicative transmission-network capacity map Svenska kraftnät, 2026-01-01. Checked 2026-09-10.
  2. Planning and Building Act guidance Boverket, 2026-01-01. Checked 2026-09-10.