EdgeConneX
Data-centre developer and operator, described in its own February 2026 notice as an EQT portfolio company.
On 27 February 2026 EdgeConneX said it looks to develop a campus in Skellefteå on a site to be acquired from Lyten. On 24 September 2026 Skellefteå granted a building permit for the first two buildings, DC01 and DC02.
A profile is not a quality stamp.
Related projects
Related news
Sources
- EdgeConneX looks to enter Sweden with a Skellefteå campus — EdgeConneX, 2026-02-27. Checked 2026-09-12.
- Notice of permit: data centres DC01 and DC02 on Ackumulatorn 3 (case 2026-3140) — Skellefteå kommun, 2026-09-28. Checked 2026-10-20.